Kata Kunci ; Produktivitas Ready Mix, OMAX (Objecktive Matrix).Abstrak
PT Pionerbeton Indiustri is one of the companies engaged in the production of ready mix concrete, which is a subsidiary of PT Indocement Tunggal Perkasa, Tbk for casting projects located in JL. Ahmad yani (South Ringroad), Padukuhan Modalan RT 02, Banguntapan Village, Banguntapan District, Bantul Regency DIY. The method used in the study was to use the OMAX (Objective Matrix) method. This research was conducted for 12 months, namely January-December 2021. This research was conducted using the OMEX (Objecktive Matrix) method, so that in processing the data is carried out by following the steps of OMAX (Objecktive Matrix). The purpose of this study is to determine the ratios that most affect the rise and fall of productivity levels with the Objecktive Matrix method. Based on calculations using the Objecktive Matrix method, it shows that the productivity data of PT Pionirbeton Industri has a low value in September material, which is 471,134,817 due to the late supply of raw materials which results in decreased productivity in September.
Referensi
[2] Irwansyah, D., Erliana, C. I., Fadlisyah, F., Ula, M., & Fahrozi, M. (2022). Increasing Productivity in CPO Production Using The Objective Matrix Method. International Journal of Engineering, Science and Information Technology, 2(2), 14–20. https://doi.org/10.52088/ijesty.v2i2.232
[3] Irwansyah, D., & Hidayat, M. (2021). Usaha Peningkatan Produktivitas Pada Produksi Cpo Dengan Menggunakan Metode Objective Matriks (Omax) Di Pt. Inka Bina Agro Wisesa. Industrial Engineering Journal, 10(1). https://doi.org/10.53912/iejm.v10i1.622
[4] Jinbo, J., Wenjing, Z., Jie, J. I. N., Jiyun, L. I., & Xudong, P. (2020). A comprehensive multi-objective , multi-parameter and multi-condition optimization of a spiral groove in dry gas seals. https://doi.org/10.3901/CJME.2020.0425.100
[5] Rizaldi, M. F., & Mesta, H. A. (2021). OMISS Operations Management and Information System Studies Green product quality : A gray servqual approach. 1(1), 20–29. https://doi.org/10.24036/jkmb.xxxxxxxx
[6] Sinaga, K., Lie, K., Williams, N., & Sunarni, T. (2021). Productivity Analysis Of Filling Machine With The Objective Matrix (OMAX) Method. ABDIMAS TALENTA: Jurnal Pengabdian Kepada Masyarakat, 6(1), 32–39. https://doi.org/10.32734/abdimastalenta.v6i1.5444
[7] Studi, P., Industri, T., Teknik, F., & Malang, U. M. (2022). Jurnal Indonesia Sosial Teknologi : p – ISSN : 2723 - 6609 PENERAPAN KONSEP BALANCED SCORECARD DAN OBJECTIVE MATRIX UNTUK PERANCANGAN SISTEM PENGUKURAN KINERJA PERUSAHAAN Abstrak Penerapan Konsep Balanced Scorecard dan Objective Matrix Untuk Perancangan S. 3(2), 266–271.
[8] Sudiman, S., & Fahrudin, W. A. (2021). Perancangan Efektivitas dan Efisiensi untuk Peningkatan Produktivitas Lini Produksi Wellhead dengan Metode Objective Matrix. Jurnal INTECH Teknik Industri Universitas Serang Raya, 7(1), 15–22. https://doi.org/10.30656/intech.v7i1.2590
[9] Supriyadi, E., Junaedi, J., & Oktaviani, H. (2021). Analysis of Rtrto60K16 Pkx Yarn Production Process With Objective Matrix (Omax) Method. SINTEK JURNAL: Jurnal Ilmiah …, 59–67. https://doi.org/10.24853/sintek.15.1.59-67
[10] Wibisono, D. (2019). Analisis Produktivitas Dengan Menggunakan Pendekatan Metode Objective Matrix (OMAX) Studi Kasus di PT. XYZ. Jurnal Optimasi Teknik Industri (JOTI), 1(1), 1. https://doi.org/10.30998/joti.v1i1.3423